Quantcast



Fluor on board at plant

First Posted: 7:53 am - November 6th, 2015

Staff Report



South Carolina Electric & Gas Company and its partners placed the 2.4- million pound CA01 module at the V.C. Summer plant in Jenkinsville on July 23 using one of the world’s largest cranes, a heavy lift derrick that stands approximately 560 feet tall. Fluor Corporation or its affiliates will now be involved with the project as a subcontracted construction manager. Fluor has experience with many large electric generating projects, including V.C. Summer Unit 1.
Courtesy photo
Story Tools:


Font Size:


Social Media:

JENKINSVILLE – The Santee Cooper board of directors authorized a change to the contract for its joint expansion of V.C. Summer Nuclear Station with partner South Carolina Electric & Gas Company that will provide more certainty on price and schedule.

The board approved a resolution authorizing Santee Cooper President and CEO Lonnie Carter to execute a new Limited Agency Agreement with SCE&G, reflecting approval of an amended Engineering, Procurement and Construction (EPC) Agreement SCE&G will execute with the consortium building two new AP1000 nuclear power units at V.C. Summer.

“This is a positive development in the new nuclear project, because it offers significant incentives and penalties associated with bringing the units online in 2019 and 2020,” Carter said. “The new fixed price option would limit construction costs if we choose to exercise it. Finally, we are confident that Fluor will bring solid expertise and resources that will keep the project on track to deliver 2,200 megawatts of clean energy to South Carolina by 2020.”

The amended EPC Agreement reflects that Westinghouse Electric Company LLC intends to acquire the stock of Stone & Webster from Chicago Bridge & Iron. Following that acquisition, Stone & Webster will continue to be a party to the EPC Agreement for the V.C. Summer expansion, but as a subsidiary of WEC instead of CB&I.

WEC intends to engage Fluor Corporation or its affiliates as a subcontracted construction manager. Fluor has experience with many large electric generating projects, including V.C. Summer Unit 1.

The amended EPC Agreement will tie payments going forward to a milestone schedule, increase liquidated damages and add a fixed-price option that if exercised would significantly shift the remaining financial risk to the contractors. Under the base amendment, Santee Cooper will pay an additional $112.5 million to settle known construction cost increases agreed to last year.

If the fixed-cost option is chosen and approved, Santee Cooper’s share would be another $800 million in exchange for EPC Agreement price certainty for the balance of the construction project.

Santee Cooper is South Carolina’s largest power producer, the largest Green Power generator and the ultimate source of electricity for 2 million people across the state. Through its low-cost, reliable and environmentally responsible electricity and water services, and through innovative partnerships and initiatives that attract and retain industry and jobs, Santee Cooper powers South Carolina. To learn more, visit www.santeecooper.com.

South Carolina Electric & Gas Company and its partners placed the 2.4- million pound CA01 module at the V.C. Summer plant in Jenkinsville on July 23 using one of the world’s largest cranes, a heavy lift derrick that stands approximately 560 feet tall. Fluor Corporation or its affiliates will now be involved with the project as a subcontracted construction manager. Fluor has experience with many large electric generating projects, including V.C. Summer Unit 1.
http://heraldindependent.com/wp-content/uploads/2015/11/web1_vcsummer01.jpgSouth Carolina Electric & Gas Company and its partners placed the 2.4- million pound CA01 module at the V.C. Summer plant in Jenkinsville on July 23 using one of the world’s largest cranes, a heavy lift derrick that stands approximately 560 feet tall. Fluor Corporation or its affiliates will now be involved with the project as a subcontracted construction manager. Fluor has experience with many large electric generating projects, including V.C. Summer Unit 1. Courtesy photo

Staff Report

englewoodindependent

Circulars

Featured Businesses

Poll

Info Minute


Gas Prices provided by GasBuddy.com